Question: QUESTION 4 : After completing the work up to the slab - on - fill, what is the estimated volume ( m 3 ) of

QUESTION 4: After completing the work up to the slab-on-fill, what is the estimated volume (m3) of soil to be disposed? Considering a swell factor of 25% on the excavated soil.
Note:
Assuming all backfill material came from
QUESTION 5: In connection to Question 4, given that each elf truck has a capacity of 3 m3, how many trucks are required to transport the soil. the excavated soil