Question: Question 4 (b) A new start-up company has started to assemble robots for floor cleaning. The robots are assembled using various components shown in Table

Question 4 (b) A new start-up company has started to assemble robots for floor cleaning. The robots are assembled using various components shown in Table 3. The numbers within the brackets show the units of the component required to produce each unit of the item. All the components are ordered lot-for-lot except G which must be ordered in multiples of 80 units. Assume that the components are used only for this particular robot.

Item Lead Time (Weeks) On Hand Components
Robot 2 10 B, G, C(3)
B 1 5 E, F
C 1 20 G(2), H
E 2 4 -
F 3 8 -
G 2 15 -
H 1 10

-

(i) Apply the Material Requirements Planning (MRP) approach to develop the bill of materials for the robot.

This is all the details, there aren't any more.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!