Question: Question 4 Budget and schedule information for each activity in a project is contained in the: Work breakdown structure. Project goal criteria. Scope baseline. Management
Question
Budget and schedule information for each activity in a project is contained in
the:
Work breakdown structure.
Project goal criteria.
Scope baseline.
Management plan.