Question: QUESTION 4 Earned value calculations are highly dependent on accurate percent completion reporting. Which of the following is not a rule that project managers can

QUESTION 4 Earned value calculations are highly

QUESTION 4 Earned value calculations are highly dependent on accurate percent completion reporting. Which of the following is not a rule that project managers can implement to ensure consistent percent completion reporting? O % complete is proportional to work completed 100% complete at the beginning of a task 100% complete at the end of a task 50% at the beginning of a task, 50% at the end of a tasks