Question: QUESTION 4 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Job 1 2 3

QUESTION 4 Five jobs are to be processed through

QUESTION 4 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Job 1 2 3 4 5 3 6 8 4 2. Processing Time Due Date 4 8 12 21 15 Determine the sequence to minimize Mean Flow Time. Job sequence: QUESTION 5 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Job 1 2 3 4 5 3 6 00 4 4 Processing Time Due Date 4 8 12 21 15 Determine the sequence to minimize Average Tardiness. ob sequence