Question: QUESTION 4 : Johnson is trying to understand the consequences of increasing the batch size from 8 lbs to 2 0 lbs . Calculate the
QUESTION : Johnson is trying to understand the consequences of increasing the batch size from lbs to lbs Calculate the THROUGHPUT RATE of each stage for a batch size of lb then answer the questions below, paying attention to the requested units. Where the answer is not a whole number, round to two decimal places.
a If Johnson were to increase the batch size to lbs which activity is the bottleneck? Please type the letter of your desired answer below.
a Batching
b Mixing
c Extruding
d Frying
e Cooling
f Customizing
Batching
A
b How many donuts could be
produced every hour on average using a batch size of lb
A
c If the batch size were increased to lbs which activities would have a longer THROUGHPUT TIME in minutes for each batch? Please type the letter of your desired answer below.
a None of the activities would have a longer throughput time.
b Batching, mixing, frying and cooling
c Extruding and customizing
d All activities would have a longer throughput time.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock