Question: QUESTION 4 : Johnson is trying to understand the consequences of increasing the batch size from 8 lbs to 2 0 lbs . Calculate the

QUESTION 4: Johnson is trying to understand the consequences of increasing the batch size from 8 lbs to 20 lbs. Calculate the THROUGHPUT RATE of each stage (for a batch size of 20 lb) then answer the questions below, paying attention to the requested units. Where the answer is not a whole number, round to two decimal places.
a) If Johnson were to increase the batch size to 20 lbs, which activity is the bottleneck? Please type the letter of your desired answer below.
a) Batching
b) Mixing
c) Extruding
d) Frying
e) Cooling
f) Customizing
Batching
A
b) How many donuts could be
produced every hour (on average) using a batch size of 20 lb?
3120
A
c) If the batch size were increased to 20 lbs, which activities would have a longer THROUGHPUT TIME (in minutes) for each batch? Please type the letter of your desired answer below.
16
5
7
a) None of the activities would have a longer throughput time.
b) Batching, mixing, frying and cooling
c) Extruding and customizing
d) All activities would have a longer throughput time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!