Question: QUESTION 4 Use the earned value table to determine the estimated cost to completion given the indicated state of the project. % Activity 5 10


QUESTION 4 Use the earned value table to determine the estimated cost to completion given the indicated state of the project. % Activity 5 10 15 20 125 30 35 Plan Complete 850 350 1,200 100% B 400 125 525 100% 1,275 650 1,925 100% 2800 14,500 350 7,650 95% 680 400 1,080 75% 125 875 1,000 80% G 300 1200 1,500 45% Monthly Plan 850 750 1,400 3,450 5, 180 1,175 2,075 14,880 Monthly Act 900 650 1,350 3,875 4,780 850 2,000 O $16, 173 O $18, 164 O $15,966 O $17,441
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
