Question: QUESTION 4 Using the data in problem # 1 , what is the earliest start time for activity D ? 1 3 1 5 1

QUESTION 4
Using the data in problem #1, what is the earliest start time for activity D?
13
15
12
9
1.5 points
QUESTION 5
Using the data in problem #1, what is the latest start time for activity B?
6
9
12
15