Question: QUESTION 4 Where in a project schedule is a good place to plan a buffer? Immediately after a highly uncertain task. Where scarce resources are
QUESTION
Where in a project schedule is a good place to plan a buffer?
Immediately after a highly uncertain task.
Where scarce resources are needed.
At the end of the project.
All of these are good places to plan buffers.