Question: Question 42 View Policies Current Attempt in Progress The predetermined overhead rate for Vaughn Manufacturing is $5, comprised of a variable overhead rate of $3

Question 42 View Policies Current Attempt in Progress The predetermined overhead rate for Vaughn Manufacturing is $5, comprised of a variable overhead rate of $3 and a fixed rate of $2. The amount of budgeted overhead costs at normal capacity of $150000 was divided by normal capacity of 30000 direct labor hours, to arrive at the predetermined overhead rate of $5. Actual overhead for June was $13024 variable and $7920 fixed, and 2200 units were produced. The direct labor standard is 2 hours per unit produced. The total overhead variance is $2640 F. $1056 U. $2640 U. O $1056 F
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts