Question: QUESTION 4[20] The table below provides the duration estimates in days for a construction project. begin{tabular}{|l|l|l|l|l|}hline Activity & Predecessor & Optimistic Time & Most Likely
QUESTION 4[20] The table below provides the duration estimates in days for a construction project. \begin{tabular}{|l|l|l|l|l|}\hline Activity & Predecessor & Optimistic Time & Most Likely Time & Pessimistic Time \\\hline A & - & 4 & 7 & 10\\\hline B & - & 2 & 9 & 10\\\hline C & A,B & 2 & 5 & 8\\\hline D & C & 16 & 19 & 28\\\hline E & C & 6 & 9 & 24\\\hline F & E & 1 & 7 & 13\\\hline G & C & 4 & 10 & 28\\\hline H & D,F & 2 & 5 & 14\\\hline I & G,F & 5 & 8 & 17\\\hline J & H,l & 2 & 5 & 8\\\hline \end{tabular}4.1 Determine the expected completion time for each activity. (5 marks)