Question: QUESTION 4[20] The table below provides the duration estimates in days for a construction project. begin{tabular}{|l|l|l|l|l|}hline Activity & Predecessor & Optimistic Time & Most Likely

QUESTION 4[20] The table below provides the duration estimates in days for a construction project. \begin{tabular}{|l|l|l|l|l|}\hline Activity & Predecessor & Optimistic Time & Most Likely Time & Pessimistic Time \\\hline A & - & 4 & 7 & 10\\\hline B & - & 2 & 9 & 10\\\hline C & A,B & 2 & 5 & 8\\\hline D & C & 16 & 19 & 28\\\hline E & C & 6 & 9 & 24\\\hline F & E & 1 & 7 & 13\\\hline G & C & 4 & 10 & 28\\\hline H & D,F & 2 & 5 & 14\\\hline I & G,F & 5 & 8 & 17\\\hline J & H,l & 2 & 5 & 8\\\hline \end{tabular}4.1 Determine the expected completion time for each activity. (5 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!