Question 43 2 pts Que Time Running Attempt due: A 48 Minutes, You are the ScrumMaster for an Agile team. The team's story point velocity over the last 5 iterations is 40, 35, 52, 48, 46. There are 396 points remaining to completion. The Product Owner asks you which iteration your team will complete the project? Your answer is.....We will complete in Iteration Next > Previous OM LG MAIL SONY ASSIST WEB VNO Inser Pause Breaks F12 F11 Pit Sc Sys Ra F10 F9 F8 // * & 7