QUESTION 47 Given the project management software report below, determine the cost performance index (CPI) for the entire projcet to date. Round your result to 3 decim places, if applicable. ID Task Name 3 Need Survey 4 Set Product Specs 5 Shelf Life Report 6 Nutrition Support 7 ID and Vet Fruit Suppliers 8 Pre-Production Contracts 10 Equipment Rehab Production Trials 12 Quality Trials 13 Quality Metrics 14 Process Refinement 15 Quality Training 17 Market Testing 18 Package Design 19 Select Distributors 21 FDA Certification 22 Process Patent Draft, Revie 23 TM Registration 24 Prep Product Launch Planned Value - PV (BCWS) $76,800.00 $100,800.00 $28,800.00 $14,400.00 $$9,395.00 $0.00 $528,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $62,633.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 ==== $820,828.33 Earned Value - EV (BCWP) $76,800.00 $100,800.00 $28,800.00 $14,400.00 $9,395.00 $0.00 $448,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $62,633.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 ======= $741,628.33 AC (ACWP) $76,800.00 $114.240.00 $25,920.00 $14,400.00 $9,395.00 $0.00 $448,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $62,633.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $752,188.33
Qusstion A7 Given the project management software report below, determine the cost perfomance index (CPI) for the entire projcet to date: Round your refult to 3 deci places, if applicable Qusstion A7 Given the project management software report below, determine the cost perfomance index (CPI) for the entire projcet to date: Round your refult to 3 deci places, if applicable