Question: Question 5 0 / 1 point When creating a WBS for the project, the following is the correct order of the decomposition? Question options: a

Question 50/1 point
When creating a WBS for the project, the following is the correct order of the decomposition?
Question options:
a) Project, work package, deliverable, sub-deliverable, lowest sub-deliverable
b) Work package, deliverable, items, workers, activities
c) Work package, deliverable, sub-deliverable, lowest sub-deliverable, verb
d) Deliverable, sub-deliverable, lowest sub-deliverable, project, activities
e) Project, deliverable, sub-deliverable, lowest sub-deliverable, work package
Question 160/1 point
The highest priority among an organisation's strategic choice elements is________?
Question options:
a) Task
b) Goal
c) Objective
d) Mission
Question 170/1 point
In project management, risk is ___________
Question options:
a) An estimation technique
b) A known event
c) An unknown event
d) An assumption
Question 180/1 point
You are a project manager for your organisation and progressing nicely through the procurement of resources for a one-day event. Which of the following stakeholders should receive a copy of the procurement documentation?
Question options:
a) Customers
b) The sellers, you are procuring from
c) The functional manager within the organisation
d) Your project sponsor
Question 200/1 point
A project has three paths with the following time duration in days.
A-B-C-D has 25 days. A-E-C-D has 20 days and A-F-D has a 21 days.
Which of the following statements is TRUE?
Question options:
a) The expected duration of this project is 25days.
b) A-F-D is the shortest path and the critical path
c) A-E-C-D has 20 days, so it is the shortest time it will take this project to finish
d) The expected duration is 25+20+21=66 days
Question 220/1 point
Which of the following is not a characteristic of a project?
Question options:
a) No definite end date
b) Creates a product, service, output, result or deliverables
c) Definite start date
d) An expenditure
Question 230/1 point
Which of the following is a CORRECT Milestone statement?
Question options:
a) Picked all team members 13th Feb to 25th Mar
b) Resource allocation agreed - February 30
c) Components must pass EU energy ratings
d) All appliances for the apartment is fully installed- End of project
e) Work allocation agreed February 14
Question 260/1 point
A new software installation project is in progress. The project manager is working with the quality assurance department to improve everyone's confidence that the project will satisfy the quality standards. Which of the following MUST they have before they start this process?
Question options:
a) Quality improvement
b) Quality control measurements
c) Quality problems
d) Rework plans
Question 280/1 point
When projects fail, it typically happen_____
Question options:
a) Towards the end of the PLC
b) Because the Project Manager is a graduate
c) In the middle of a PLC during execution of the plan
d) At the beginning of PLC because of poor scope
Question 370/1 point
A project with an objective to reduce to amount of waste in a manufacturing process is an example of a ____ driver?
Question options:
a) Operational - support current processes of the manufacturing process
b) Compliance - must do projects for a manufacturer
c) Strategic - long term mission of the manufacturing process
d) Operational - supports business case for the manufacturer
e) Strategic product mission statement
Question 460/1 point
A software development project is most likely to fail _____
Question options:
a) At the beginning of PLC because of poor scope
b) Towards the end of the PLC
c) Because the Project Manager is a graduate
d) In the middle of a PLC during execution of the plan
Question 490/1 point
Which of the following does NOT a typical activity in the execution stage of Larson and Grays (2013) simple project life cycle model?
Question options:
a) Preparing schedules for the project
b) Preparing a status report
c) Reviewing cost and schedule forecasts
d) Reviewing and controlling how change requests are handled
e) Checking quality of work done
Question 510/1 point
The table below is cash inflow information for two projects with the different initial financial outlays. The project sponsor is interested in the best return on investment and would like your advice on which project to undertake.
Year Project Android Project Apple
0(60,000)(50,000)
115,00015,000
210,00010,000
38,00010,000
412,00010,000
Question options:
a) Neither, both have the same ROI
b) Undertake Project Apple it has a better ROI
c) Undertake Project Apple, it has a better name
d) Undertake Project Android, it has a better year 0
e) Undertake Project Android it has a better ROI

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!