Question: Question 5 0 / 1 point When creating a WBS for the project, the following is the correct order of the decomposition? Question options: a
Question point
When creating a WBS for the project, the following is the correct order of the decomposition?
Question options:
a Project, work package, deliverable, subdeliverable, lowest subdeliverable
b Work package, deliverable, items, workers, activities
c Work package, deliverable, subdeliverable, lowest subdeliverable, verb
d Deliverable, subdeliverable, lowest subdeliverable, project, activities
e Project, deliverable, subdeliverable, lowest subdeliverable, work package
Question point
The highest priority among an organisation's strategic choice elements is
Question options:
a Task
b Goal
c Objective
d Mission
Question point
In project management, risk is
Question options:
a An estimation technique
b A known event
c An unknown event
d An assumption
Question point
You are a project manager for your organisation and progressing nicely through the procurement of resources for a oneday event. Which of the following stakeholders should receive a copy of the procurement documentation?
Question options:
a Customers
b The sellers, you are procuring from
c The functional manager within the organisation
d Your project sponsor
Question point
A project has three paths with the following time duration in days.
ABCD has days. AECD has days and AFD has a days.
Which of the following statements is TRUE?
Question options:
a The expected duration of this project is days.
b AFD is the shortest path and the critical path
c AECD has days, so it is the shortest time it will take this project to finish
d The expected duration is days
Question point
Which of the following is not a characteristic of a project?
Question options:
a No definite end date
b Creates a product, service, output, result or deliverables
c Definite start date
d An expenditure
Question point
Which of the following is a CORRECT Milestone statement?
Question options:
a Picked all team members th Feb to th Mar
b Resource allocation agreed February
c Components must pass EU energy ratings
d All appliances for the apartment is fully installed End of project
e Work allocation agreed February
Question point
A new software installation project is in progress. The project manager is working with the quality assurance department to improve everyone's confidence that the project will satisfy the quality standards. Which of the following MUST they have before they start this process?
Question options:
a Quality improvement
b Quality control measurements
c Quality problems
d Rework plans
Question point
When projects fail, it typically happen
Question options:
a Towards the end of the PLC
b Because the Project Manager is a graduate
c In the middle of a PLC during execution of the plan
d At the beginning of PLC because of poor scope
Question point
A project with an objective to reduce to amount of waste in a manufacturing process is an example of a driver?
Question options:
a Operational support current processes of the manufacturing process
b Compliance must do projects for a manufacturer
c Strategic long term mission of the manufacturing process
d Operational supports business case for the manufacturer
e Strategic product mission statement
Question point
A software development project is most likely to fail
Question options:
a At the beginning of PLC because of poor scope
b Towards the end of the PLC
c Because the Project Manager is a graduate
d In the middle of a PLC during execution of the plan
Question point
Which of the following does NOT a typical activity in the execution stage of Larson and Grays simple project life cycle model?
Question options:
a Preparing schedules for the project
b Preparing a status report
c Reviewing cost and schedule forecasts
d Reviewing and controlling how change requests are handled
e Checking quality of work done
Question point
The table below is cash inflow information for two projects with the different initial financial outlays. The project sponsor is interested in the best return on investment and would like your advice on which project to undertake.
Year Project Android Project Apple
Question options:
a Neither, both have the same ROI
b Undertake Project Apple it has a better ROI
c Undertake Project Apple, it has a better name
d Undertake Project Android, it has a better year
e Undertake Project Android it has a better ROI
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock