Question: Question 5 : ( 1 0 % ) The arrow network shown below is from a multi - complex residential project. Each complex is comprised

Question 5: (10%)
The arrow network shown below is from a multi-complex residential project. Each complex
is comprised of four buildings.
Each building has the following activities:
Excavation. (4 days)
Form and Pour Foundations and Slab. (14 days)
Frame Building. (16 days)
Brickwork.
The project manager needs to plan the start date of the brickwork activity. The Brickwork
activity requires 96 WH for each building, and the project manager is planning to use a
brickwork crew working 24 WH per day (3-person crew *8 hours/day).
For one complex only (i.e.4 buildings), determine, using the Linear Scheduling Method, an
appropriate start time for the brickwork activity to enable it to continue without interruption.
Question 5 : ( 1 0 % ) The arrow network shown

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!