Question: Question 5 (1 point) v Saved 1. The direct labour times required to produce the first four units of a new product are shown below:

Question 5 (1 point) v Saved 1. The direct labour

Question 5 (1 point) v Saved 1. The direct labour times required to produce the first four units of a new product are shown below: Unit Number Direct Labour Hours 1,000 900 810 729 to Based on this data the estimated learning curve is: 80% 70% 100% O 90% 085%