Question: Question 5 1 pts Given the following task time estimates (HOURS), a. How long is the project length? b. What tasks form the critical path?

 Question 5 1 pts Given the following task time estimates (HOURS),

Question 5 1 pts Given the following task time estimates (HOURS), a. How long is the project length? b. What tasks form the critical path? c. What is the LS/LF for activity D.? d. How much slack is there in activity C? How much slack in activity D? e. What if activity D. was delayed by 6 hours, what would be the project length and critical path? f. Referring to letter e., how much slack would be in activity B

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!