Question: Question 5 [10 marks] Suppose the average daily float is $5 million with a weighted average delay of 5 days. Consider the following questions a.
![Question 5 [10 marks] Suppose the average daily float is $5](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/09/66ed9f706ef86_87966ed9f6fe4d2d.jpg)
Question 5 [10 marks] Suppose the average daily float is $5 million with a weighted average delay of 5 days. Consider the following questions a. What is the total amount unavailable to earn interest? b. What is the NPV of a project that could reduce the delay by 4 days if the cost is $8 million? Is it worthwhile doing such an effort? Useful formulas: NPV of eliminating the float =( Total amount unavailable to earn interest ( original delay days - reduced days) Average daily float) - cost of float elimination
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
