Question: Question 5 (15 points): Consider a real-time system with three periodic tasks. Task A has period of 75 units and requires 15 units of processing

Question 5 (15 points): Consider a real-time system with three periodic tasks. Task A has period of 75 units and requires 15 units of processing time. Task B has period 50 units and requires 20 units of processing time. Task C has period of 100 units and requires 20 units of processing time. Suppose that these tasks are all arrive at time 0, and they are scheduled with static priority using the Rate Monotonic Scheduling (RMS) model. a. Is the RMS condition for guaranteeing the existence of a feasible schedule satisfied by this system? b. Does a feasible schedule exist when using RM based scheduling of the tasks in this system? If yes, then show a feasible schedule, otherwise show a case where a task will miss its deadline