Question: Question 5 ( 2 0 Marks ) Assume the following information is provided for your project for 5 activities. Normal Crashed Activity Predecessor Duration (
Question Marks
Assume the following information is provided for your project for activities.
Normal Crashed
Activity Predecessor Duration Weeks Cost Duration Weeks Cost
A None R R
B A R R
C B R R
D C R R
E D R R
Required:
a Calculate the crash cost per period
Marks
b Which activity will you suggest be crashed? Justify your answer.
Marks
c Crashing is also known as acceleration where the duration of an activity is reduced to meet project schedule requirements.
Marks
Analyse some of the methods you have studied of shortening a project. Apply these methods to your project in order to shorten the duration.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
