Question: Question 5 ( 2 0 Marks ) Assume the following information is provided for your project for 5 activities. Normal Crashed Activity Predecessor Duration (

Question 5(20 Marks)
Assume the following information is provided for your project for 5 activities.
Normal Crashed
Activity Predecessor Duration (Weeks) Cost Duration (Weeks) Cost
A None 2 R20001 R1000
B A 3 R50001 R500
C B 4 R80002 R1000
D C 3 R100001 R2000
E D 4 R200002 R2000
Required:
a) Calculate the crash cost per period
(5
Marks)
b) Which activity will you suggest be crashed? Justify your answer.
(2
Marks)
c) Crashing is also known as acceleration where the duration of an activity is reduced to meet project schedule requirements.
(13
Marks)
Analyse some of the methods you have studied of shortening a project. Apply these methods to your project in order to shorten the duration.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!