Question: QUESTION 5 ( 2 0 Marks ) Using the data in the table below, create the project schedule using normal times. Determine the order in

QUESTION 5(20 Marks)
Using the data in the table below, create the project schedule using normal times. Determine
the order in which you would crash the project 1 day, 2 days, etc. until it is in an all crash
mode. Identify how much it would cost for each day you crash the schedule.
Activity Predecessor
Normal
time
Normal
cost
Crash
time
Crash
cost
Crash cost per
day
A B 52004350
B 82208220
C B 62504650
D A 95005600
E A,C 101509500
F E 105009650
G D,F 84006900