Question: Question 5 ( 2 points ) If resource demand varies widely over the life of the project, the project manager can try to use slack

Question 5(2 points)
If resource demand varies widely over the life of the project, the project manager can try to use slack (delaying noncritical activities) to accommodate insufficient resources. This process is called q,
resource scheduling
resource smoothing
resource-constrained scheduling
splitting
resource accommodation