Question: Question 5 ( 2 points ) If resource demand varies widely over the life of the project, the project manager can try to use slack
Question points
If resource demand varies widely over the life of the project, the project manager can try to use slack delaying noncritical activities to accommodate insufficient resources. This process is called
resource scheduling
resource smoothing
resourceconstrained scheduling
splitting
resource accommodation
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
