Question: Question 5 (2 points) Your sampling plan is n = 125, C = 2. What is the probability of accepting a lot from your supplier

Question 5 (2 points) Your sampling plan is n =

Question 5 (2 points) Your sampling plan is n = 125, C = 2. What is the probability of accepting a lot from your supplier that has a defective rate of 1.0%? 0.869 O 0.955 0.899 O 0.778 O 0.955 0.914 0.981 199+ si # KB (97