Question: Question 5 20 Marks Consider the three projects A, B, and C. The cost of capital is 12 percent, and the projects have the following

Question 5 20 Marks Consider the three projects A, B, and C. The cost of capital is 12 percent, and the projects have the following expected cash flows: Project A Project B Project C Now -R150 000-R300 000 -R150 000 End of year 1 120 000 200 000 110 000 End of year 2 80 000 180 000 90 000 Required: 5.1. What is the internal rate of return of the three projects? 5.2. What is the net present value of the three projects? 5.3. If the three projects are independent, which projects should be accepted? 5.4. If the three projects are mutually exclusive, which project should be selected? 5.5. If the total budget for the three projects is limited to R450 000, which projects should be selected