Question: Question 5 3 pts Activity Pessimistic Time Expected Time Optimistic Time A 5 3 1 B 5 3 1 C 5 3 1 D 5

Question 5 3 pts Activity Pessimistic Time

Question 5 3 pts Activity Pessimistic Time Expected Time Optimistic Time A 5 3 1 B 5 3 1 C 5 3 1 D 5 3 1 E 5 3 1 A project consists of the 5 activities listed above. All times are in weeks. All have the same pessimistic, expected and optimistic duration times. Which of the following statements is true? The project can not be completed in less than 5 weeks. No conclusions can be made regarding project completion time. The expected time to complete the project is 15 weeks. The time required to complete the project must be somewhere between 15 and 25 weeks