Question: QUESTION 5 5 . 1 There are 1 2 labourers, a mixer operator and a section leader in the concreteteam: The labourers are paid R

QUESTION 5
5.1 There are 12 labourers, a mixer operator and a section leader in the concreteteam:
The labourers are paid R140 per day.
The mixer operator is paid R190 per day
The section leader is paid R220 per day.
Calculate the total labour cost per day for the concrete team.
5.2 State SIX factors that affects productivity in construction.
(4)
(6)
TOTAL:50