Question: Question #5 ( 8 marks) In 2016, Safa construction began construction work on a 3-year contract. The contract price was $750,000. Safa uses the percentage
Question #5 ( 8 marks)
In 2016, Safa construction began construction work on a 3-year contract. The contract price was $750,000. Safa uses the percentage of completion method {PC}. PC = [Costs incurred to date]/[Total estimated costs]
The income statement for the project in 2016 is given below:
| Construction revenue | $125,000 |
| Construction expenses | 100,000 |
| Gross profit | $ 25,000 |
Calculate the initial estimated total cost, and the initial estimated total profit
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
