Question: Question 5 ( 8 marks ) The following project has three independent paths as shown in the project network diagram. The deadline to complete this

Question 5(8 marks)
The following project has three independent paths as shown in the project network diagram. The
deadline to complete this project is 46 days.
Activity
Optimistic
Time
(days)
Most
Likely
Time
(days)
Pessimistic
Time
(days)
Expected
Time
(days)
Variance
of
Activity
A 101628
B 202842
C 183042
D 151515
E 123
F 424548
a) What is the probability that this project will be delayed?
Start
A B
End
E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!