Question: Question 5 ( 8 marks ) The following project has three independent paths as shown in the project network diagram. The deadline to complete this
Question marks
The following project has three independent paths as shown in the project network diagram. The
deadline to complete this project is days.
Activity
Optimistic
Time
days
Most
Likely
Time
days
Pessimistic
Time
days
Expected
Time
days
Variance
of
Activity
A
B
C
D
E
F
a What is the probability that this project will be delayed?
Start
A B
End
E