Question: Question 5 : Consider the following graph. Here, an denotes job dependency, i . e . , 1 - > 2 means 1 is a
Question : Consider the following graph. Here, an denotes job dependency, ie
means is a prerequisite of Then, apply DFS to find a feasible job schedule. You need to
show the start and finish time for each node.
Special Rule: If multiple options either for traversal or
restarting DFS exist at any step, pick the job with a
smaller index.
For example, we can start DFS from any node. However,
according to the special rule, we must start DFS from
Node