Question: Question 5 Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Discount Cash Flow Cash Flow Cash
Question 5 Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Discount Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow Rate A -100 40 50 80 N/A 0.12 IB -73 30 30 30 30 0.12 The payback period for project A is closest to O O O O 1.9 years 2.3 years 2.6 years 2.1 years