Question: Question 5 : Design and Head Loss Calculations for Bar Screen in Water Treatment ( 3 marks ) A water treatment plant receives a flow

Question 5: Design and Head Loss Calculations for Bar Screen in Water
Treatment (3 marks)
A water treatment plant receives a flow of 24,000m3? day.
A bar screen is used to remove the coarse waste. The velocity in the approach channel (v) is 0.5ms and the flow-through velocity of the clean screen (V) is 0.8ms. Calculate the required open screen area to achieve this screen velocity during treatment of the rainwater flow.
Calculate the head loss of this clean screen using the friction coefficient C=0.7.
Question 5 : Design and Head Loss Calculations

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!