Question: Question ( 5 ) : For the below project network; At the end of the 1 0 t h week, new filed data are collected

Question (5):
For the below project network; At the end of the 10th week, new filed data are collected and the
project status activities is as follows:
60% of Activity C has been completed
Remaing duration for Activity E is 2 weeks
Activity D did not start yet but it's ready to start
Determine the update schedule and the updated project completion time.