Question: QUESTION 5 In an international project, a project manager may face a problem with a local group's perception on time. This is called a .......difference.
QUESTION 5
-
In an international project, a project manager may face a problem with a local group's perception on time. This is called a .......difference.
QUESTION 6
-
The project manager does not need to communicate the purpose of his project to project stakeholders. This is the job of the project assistant.
True
False
QUESTION 7
-
Stakeholders or parties-at-interest in any project define success in the same way.
True
False
QUESTION 8
-
The ideal project manager should be __________.
a direct, technical supervisor knowledgeable in the technology of the process being used
both generalist/facilitator and have a high level of technical competence in the science of the project
a facilitator and specialist with technical credibility
a technical specialist competent in principles of robust design
QUESTION 9
-
The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the __________ functions.
technical and managerial
schedule and cost
performance and schedule
cost and performance
QUESTION 10
-
The project manager needs __________ credibility.
technical and personal
administrative and personal
technical and administrative
technical and financial
Step by Step Solution