Question: QUESTION 5 Once the project duration has been determined, it needs be converted into calender days, often but not always 5 day workweeks. True False

QUESTION 5

  1. Once the project duration has been determined, it needs be converted into calender days, often but not always 5 day workweeks.

    True

    False

QUESTION 6

  1. Undistributed labor includes job superintendent, engineers, watchmen, among others

    True

    False

QUESTION 7

  1. Productivity rates are often expressed as a number of work hours per unit of work.

    True

    False