Question: QUESTION 5 The activities required to complete a given project together with the precedence relationships among the activities are given in Table 1 3 .

QUESTION 5
The activities required to complete a given project together with the precedence
relationships among the activities are given in Table 13.
TABLE 13. Project Activity Data
What is the earliest possible finish time for Activity D?
a.
10 days.
b.
13 days.
C.
17 days.
d.
19 days.
e.
None of the above.