Question: Question 5 You are considering the following two mutually exclusive projects. Should you accept or reject these projects based on net present value (NPV) analysis?

Question 5 You are considering the following two mutually exclusive projects. Should you accept or reject these projects based on net present value (NPV) analysis? Assume the discount rate for both projects is 7 percent. Why or why not? Year Project Alpha Project Beta 0 -$320,000 $655,000 1 $292,000 $396,000 2 $165,000 $319,000 3 $107.000 $204,000 You cannot make this decision based on net present value analysis. None; because both have the negative NPV. Both; because Both projects have the positive NPV. Project Beta; because the NPV of the project Beta is greater than the NPV of the project Alpha. Project Alpha; because the NPV of the project Alpha is greater than the NPV of the project Beta