Question: Question 51 4 pts Stadium Construction Project Problem: What is the combined slack for activities D and H? ACTIVITY IMMEDIATE PREDECESSOR DURATION (days) 1 B

Question 51 4 pts Stadium Construction Project
Question 51 4 pts Stadium Construction Project Problem: What is the combined slack for activities D and H? ACTIVITY IMMEDIATE PREDECESSOR DURATION (days) 1 B A 4. A 3 D A 7 E -B 6 F CD 2 G E,F 7 H D 9 GH 4. O 3 O 4 O2 O 1