Question: Question 5.1 QUESTION 5 Answer the questions from the information provided. 5.1 5.1.1 Use the information provided below to calculate and comment on the following

 Question 5.1 QUESTION 5 Answer the questions from the information provided.

Question 5.1

QUESTION 5 Answer the questions from the information provided. 5.1 5.1.1 Use the information provided below to calculate and comment on the following variances. Direct material usage variance (3 marks) 5.1.2 Direct labour rate variance (3 marks) 5.1.3 Direct labour efficiency variance (3 marks) 5.1.4 Variable overhead expenditure variance (3 marks) INFORMATION Harpic Manufacturers makes and sells a single product from Project D. The company operates a standard costing system. Details of the budgeted and actual data for 2020 are as follows: Budgeted data Standard production costs per unit: Direct material 4 kg at a cost of R5 per kg Direct labour 2 hours at a cost of R4 per hour Variable overheads 2 hours at R2 per direct labour hour Standard production 12 000 units Actual data Direct material 41 000 kg @ R5.50 per kg Direct labour 19 000 hours @ R3.75 per hour Variable overheads R39 900 Production 10 000 units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!