Question: Question 52 1 pts 51. A task measured using the 50/50 complete rule of claiming earned value has a planned value (PV)=$500. What is the

Question 52 1 pts 51. A task measured using the

Question 52 1 pts 51. A task measured using the 50/50 complete rule of claiming earned value has a planned value (PV)=$500. What is the Earned Value (EV) if the task is 10% complete: O $500 0 $0 O $10 O $50 O $250