Question: QUESTION 57 The construction of a structure is based upon the following network shown below. Show all work in regard to mathematical calculations. a) Draw
QUESTION 57
The construction of a structure is based upon the following network shown below. Show all work in regard to mathematical calculations. 
a) Draw the project network.
b) Find the critical path activities.
c) Calculate slack for ALL activities.
d) How long will take to complete the project?
Activity A Predecessors NONE Time (days) 6 8 B BA 2 D 3 E B 5 F 5 C,D E,F,D G 6Step by Step Solution