Question: Question 6 / 1 3 table [ [ Task ID , Description,Time needed to complete,Notes ] , [ A , Conduct research, 3 weeks,Must
Question
tableTask IDDescription,Time needed to complete,NotesAConduct research, weeks,Must start todayBWrite plan, weeks,Can do while doing Task ACRegister business, week,Can do while doing all other tasksDAdvertise business, weeks,Can do while doing Task EEHire staff, weeks,Can do while doing Task D
How many weeks will it take to complete this project?
ENTER INTEGER ANSWER