Question: Question 6 (1 point) Saved For the EPQ model, the maximal on-hand inventory level is the production quantity in each production cycle. True False Question

Question 6 (1 point) Saved For the EPQ model, the

Question 6 (1 point) Saved For the EPQ model, the maximal on-hand inventory level is the production quantity in each production cycle. True False Question 7 (1 point) Saved For a given inventory system with random demand rate, a higher CSL customers' service level means that a higher SS is required. True False Question 8 (1 point) Saved For a given project, we have a precedence network for all activities of the project. All activities not on the shortest path are called critical activities. True False