Question: Question 6 ( 1 point ) Saved If the contracted work is finished 4 days late, The subcontractor will not get paid Nothing will change

Question 6(1 point)
Saved
If the contracted work is finished 4 days late,
The subcontractor will not get paid
Nothing will change in the payment
the compensation to the subcontractor will be reduced by $1,400
the contractor will pay the owner $1,400