Question: Question 6 (1 point) The status report uses earned value to measure schedule and compliance performance. Question 6 options: True False Question 7 (1 point)

Question 6 (1 point)

The status report uses earned value to measure schedule and compliance performance.

Question 6 options:

True
False

Question 7 (1 point)

Generally, the method for measuring accomplishments centers on:

Question 7 options:

Comparing earned value with the expected schedule value

Comparing earned value with the actual costs

All the above

None of the above

Question 8 (1 point)

A project monitoring system involves:

Question 8 options:

Eliminating additional costs.

Reporting current progress.

Monitoring employee's work.

Communicating final results to upper management.

Question 9 (1 point)

The WBS is used to develop a project resource schedule that is used to time-phase all work, resources, and budgets into a baseline plan.

Question 9 options:

True
False

Question 10 (1 point)

A Control Chart is used to:

Question 10 options:

Estimate current costs and compare them to projected costs.

Schedule employee resources and develop cost estimates.

Monitor past project schedule performance and current performance and to estimate future schedule trends.

Assess past financial performance and track to current financial performance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!