Question: Question 6 1 pts The Analytic Hierarchy Process is being employed in a project selection decision. One major criteria, cost, receives a weighting value of
The Analytic Hierarchy Process is being employed in a project selection decision. One major criteria, cost, receives a weighting value of 40%, which is split into short term (50\%), intermediate term (30\%), and long term (20\%). Which of these staternents is BEST? Long-term cost receives an overall weighting of 80%. There must be at least one other major criteria that has 40% weighting. Intermediate-term cost receives a weighting of 12%. Short term, intermediate term, and long term must receive overall weightings that total 100%