Question: QUESTION 6 ( 2 0 Marks ) The figure below shows that the following 3 tasks have been scheduled. Note that the task Establish an

QUESTION 6(20 Marks)
The figure below shows that the following 3 tasks have been scheduled.
Note that the task Establish an in-house relocation task team displays a duration of 7 days. After the Establish an inhouse relocation task team task, the following sub-tasks were then entered:
Identify team members 2 days
Verify availability 3 days
Appoint relocation task team 2 days
Note that the updated schedule below with the 3 sub-tasks added now shows that Establish an in-house relocation task
team displays a duration of 3 days.
6.1 Discuss how you will convert Establish an in-house relocation task team to a summary task using the
following 3 sub-tasks:
Identify team members 2 days
Verify availability 3 days
Appoint relocation task team 2 days
(10 Marks)
6.2 Demonstrate why there was a change in duration from 7 days to 3 days for the Establish an in-house
relocation task team task.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!