Question: QUESTION 6 ( 2 0 Marks ) The figure below shows that the following 3 tasks have been scheduled. Note that the task Establish an
QUESTION Marks
The figure below shows that the following tasks have been scheduled.
Note that the task Establish an inhouse relocation task team displays a duration of days. After the Establish an inhouse relocation task team task, the following subtasks were then entered:
Identify team members days
Verify availability days
Appoint relocation task team days
Note that the updated schedule below with the subtasks added now shows that Establish an inhouse relocation task
team displays a duration of days.
Discuss how you will convert Establish an inhouse relocation task team to a summary task using the
following subtasks:
Identify team members days
Verify availability days
Appoint relocation task team days
Marks
Demonstrate why there was a change in duration from days to days for the Establish an inhouse
relocation task team task.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
