Question: Question 6 (3 points) The following table provides the information necessary to construct a project network and project crash data. If you crash the project

Question 6 (3 points) The following table

Question 6 (3 points) The following table provides the information necessary to construct a project network and project crash data. If you crash the project the maximum amount possible, what is the total cost of the crashed project (total normal cost plus the cost of crashing). (Enter your response to the nearest whole number.) Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost A NONE 20 8 1000 1480 B NONE 24 20 1200 1400 NONE 14 7 700 1190 D A 10 6 500 820 E 11 5 550 772 Your Answer: Your