Question: Question 6 (5 points) Use the information in attachment capacity q2.Your company has just received some new customers. The final step of the production process

Question 6 (5 points) Use the information in attachment capacity q2.Your company has just received some new customers. The final step of the production process is to paint the product before it is shipped. The company operates 250 days per year, with one 8-hour shift. Management believes that a capacity cushion of 20% percent (beyond the allowance built into time standards) Based on the following information, determine how many paint booths are needed by the company? Less than 5 More than 8 More than 5 but less than 8 More than 3 but less than 6