Question: Question 6 5 pts Projects 1 2 3 4 5 IRR 15.6% 18% 11% 15.8% 18.5% 1st Cost 70K 40K 20K 90K 90K You have

 Question 6 5 pts Projects 1 2 3 4 5 IRR

Question 6 5 pts Projects 1 2 3 4 5 IRR 15.6% 18% 11% 15.8% 18.5% 1st Cost 70K 40K 20K 90K 90K You have $200K available to invest in multiple projects. Which is the best choice from below? A#4 & 5 B.#2 & 5 C.#2. 4. & 5 D.#1, 2, & 5 E. 3,485 CA B MacBook Pro