Question: Question 6 A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is

Question 6 A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=26, B=18, C=41. How long will it take to complete the project